Update and correction: Casey Cook reports an update to this press release: FEMA now reports $1,961,406.00 will be appropriated in federal recovery funds for the Talkeetna revetment.
Damage to the Talkeetna Revetment from the 2012 flood disaster will be repaired with $1.3 million in federal recovery funds. Casey Cook, Matanuska-Susitna Borough Emergency Manager, informed the Matanuska-Susitna Borough Assembly last week.
"Working with our partners at the State of Alaska Division of Homeland Security and Emergency Management and FEMA, we have secured funding for the cost of repairs for the Talkeetna Revetment, and will be working with them to move the recovery efforts associated with this disaster toward a conclusion," Cook said. "The scope of these recovery efforts will bring the condition of the revetment back to the pre-disaster state. We appreciate the amount of work and effort from our partners as well as our Public Works, Operations & Maintenance and Finance staff who have worked tirelessly."
Borough Manager John Moosey said the successful application took nearly five years.
"We are pleased with this hard-earned outcome," said Mat-Su Borough Manager John Moosey. "Our team led by Casey Cook put in four years of undeterred effort where most others would have given up. Senator Murkowski was instrumental at making sure that we could make our case at every turn. The great work by her, I believe, was the difference on receiving the funding," Moosey said.
The revetment is 1,000 feet long beginning west of the end of Main Street running north on the riverbank toward the railroad bridge. "It used to be a surface you could drive on but today it's a jumble of rocks," said Pam Ness, a Borough code compliance officer and a floodplain manager. The aerial image is from 2011.
For more information call Casey Cook at 861-8004 or Public Affairs Director Patty Sullivan 861-8577, This email address is being protected from spambots. You need JavaScript enabled to view it.